Please be advised that the controlled blasting operations for rock removal this summer have been completed. There will be another small round of blasting towards the final phase of the project after the old school has been torn down in the Spring of 2020.
The temporary Haul Road will be completed and turned over for construction use by 8/24. This new access road will significantly reduce truck and delivery traffic on Crosby Road through the next phase of the project.
Drilling of geo-thermal wells will be starting in August and continuing over the next few months. The construction team has also started foundation work for the new building.